Municipal Buildings Roof Repairs

Gore Bay, Ontario

completeRecreationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Gore Bay
Construction start
Feb 1, 2022(actual)
Construction end
Mar 28, 2022(actual)

Against the original forecast

  • Construction start8 months lateforecast Jun 1, 2021

Also in Gore Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59786 in the federal list. How to read these figures.