Newmarket National Homes Multi-Use Pathway
Federal contribution
$86,418
Federal share80%
of $108.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Newmarket
- Construction start
- Jul 13, 2021(actual)
- Construction end
- Oct 15, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 4, 2021
- Construction end4 months lateforecast Jun 30, 2021