Renovation of the library
Federal contribution
$422,400
Federal share80%
of $528.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège Laflèche
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Nov 5, 2021(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 1, 2021
- Construction end5 weeks lateforecast Sep 30, 2021
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59794 in the federal list. How to read these figures.