Gym floor replacement
Federal contribution
$126,134
Federal share63%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Oct 4, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end8 weeks earlyforecast Nov 27, 2021
Also in Boisbriand
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59897 in the federal list. How to read these figures.