Back to projects

Gym floor replacement

Boisbriand, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$126,134
Federal share63%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Oct 4, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end8 weeks earlyforecast Nov 27, 2021

Also in Boisbriand

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59897 in the federal list. How to read these figures.