Renovation of sanitary blocks

Sainte-Thérèse, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$476,036
Federal share80%

of $595.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 22, 2021(actual)
Construction end
Feb 15, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end2 months lateforecast Dec 14, 2021