City of Cornwall - Active Transportation

Cornwall, Ontario

completeActive TransportationCVRIS
Federal contribution
$483,786
Federal share80%

of $604.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
202220232024
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Cornwall
Construction start
May 10, 2021(actual)
Construction end
Nov 24, 2023(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Dec 31, 2023