City of Cornwall - Active Transportation
Federal contribution
$483,786
Federal share80%
of $604.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
202220232024
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Cornwall
- Construction start
- May 10, 2021(actual)
- Construction end
- Nov 24, 2023(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Dec 31, 2023
Also in Cornwall
- Cornwall Wastewater Treatment$18.5M
- Construction of Cornwall Multi Sport Facility$9.2M
- Replacement Conventional and Para Transit Buses$4.8M
- Construction of Salt Storage Facilities$1.9M
- Rehabilitation of Cast Iron Watermains on Water Street, Riverdale, and East End Neighbourhoods to improve structural and hydraulic performance.$1.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59914 in the federal list. How to read these figures.