Port Hope Wastewater Treatment Plant Improvements
Federal contribution
$184,085
Federal share80%
of $230.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Port Hope
- Construction start
- Aug 2, 2022(actual)
- Construction end
- Oct 25, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Sep 30, 2022
Also in Port Hope
- Upgrades to Port Hope Water Pollution Control Plant$4.9M
- Joint Operations Centre$1.7M
- Dorset Street Standpipe Replacement - Phase 1$1.4M
- Construction of a New Seniors/Multipurpose Community Centre as an addition at the Town Park Recreation Centre$1.2M
- Sanitary Sewer Twinning of the gravity sewer from Hope Street to the Sewage Treatment Plant to mitigate by-pass during wet weather events$772.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59922 in the federal list. How to read these figures.