Eliot River Elementary Building Phase 1

Cornwall, Prince Edward Island

completeEducation, Training and ChildcareCVRIS
Federal contribution
$680,000
Federal share80%

of $850.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Aug 26, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 3, 2021
  • Construction end13 months earlyforecast Oct 7, 2023