Public Works Garage Upgrades
Federal contribution
$554,674
Federal share80%
of $693.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Chatham-Kent
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start10 months earlyforecast May 1, 2022
- Construction end12 months lateforecast Dec 31, 2022
Also in Chatham-Kent
- Flood Mitigation along Thames and Sydenham Rivers: Slope Stabilization and Levee to Retain Recurrent River Flooding$16.6M
- YMCA of Chatham-Kent Facility Renewal$4.2M
- HVAC upgrade for schools and childcare; Water fill station; Window Replacement$3.0M
- Highway 401 - Essex Road to Bloomfield Road Eastbound Lanes$2.5M
- HVAC Upgrades and/or Window Replacement$2.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59941 in the federal list. How to read these figures.