Tree Planting at City of Waterloo Parks and Woodlots
Federal contribution
$105,334
Federal share80%
of $131.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Waterloo
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Nov 4, 2022(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Dec 31, 2022