COVID-19 Infrastructure Improvements - Sarnia

Sarnia, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$191,200
Federal share80%

of $239.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 15, 2021(actual)
Construction end
Apr 17, 2023(actual)

Against the original forecast

  • Construction end8 months earlyforecast Dec 30, 2023