Replacement of a staircase
Federal contribution
$238,614
Federal share80%
of $298.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 23, 2021(actual)
- Construction end
- May 26, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end4 months lateforecast Jan 31, 2022
Also in Blainville