HVAC Upgrades Program
Federal contribution
$2.7M
$2,683,200
Federal share80%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Hamilton
- Construction start
- Mar 16, 2023(actual)
- Construction end
- Jul 13, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 1, 2022
- Construction end2 months lateforecast Apr 30, 2024