HVAC Upgrades Program

Hamilton, Ontario

completeVentilationCVRIS
Federal contribution
$2.7M
$2,683,200
Federal share80%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Hamilton
Construction start
Mar 16, 2023(actual)
Construction end
Jul 13, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast Dec 1, 2022
  • Construction end2 months lateforecast Apr 30, 2024