Gage Park Walkways Redevelopment

Hamilton, Ontario

completeActive TransportationCVRIS
Federal contribution
$687,412
Federal share80%

of $859.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
2022
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
City of Hamilton
Construction start
Sep 30, 2021(actual)
Construction end
Nov 21, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 25, 2021
  • Construction end5 months lateforecast Jun 17, 2022

Also in Hamilton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60006 in the federal list. How to read these figures.