Harry Turnbull Park Revitalization
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the City of Sarnia.
- Construction start
- May 1, 2023(actual)
- Construction end
- Oct 13, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 5, 2022
- Construction end2 weeks earlyforecast Oct 27, 2023
Also in Sarnia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60036 in the federal list. How to read these figures.