Back to projects

2021 City Wide Trail Improvements P21-155

St. Catharines, Ontario

completeActive TransportationCVRIS
Federal contribution
$824,749
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
202220232024
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 1, 2021(actual)
Construction end
Dec 21, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 30, 2021