Millennium Recreation Trail Section 2 Development
Federal contribution
$1.0M
$1,018,782
Federal share80%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Niagara Falls
- Construction start
- Sep 13, 2021(actual)
- Construction end
- Dec 11, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Sep 27, 2023
Also in Niagara Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60131 in the federal list. How to read these figures.