Federal contribution
$640,000
Federal share80%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022202320242025
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2022(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2022