Lake Commando Multi-Use Pathway Connecting Link
Federal contribution
$106,398
Federal share80%
of $133.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
202220232024
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Cochrane
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start14 months lateforecast Jul 4, 2022
- Construction end12 months lateforecast Dec 30, 2022