Lake Commando Multi-Use Pathway Connecting Link

Cochrane, Ontario

completeActive TransportationCVRIS
Federal contribution
$106,398
Federal share80%

of $133.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
202220232024
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Cochrane
Construction start
Sep 1, 2023(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start14 months lateforecast Jul 4, 2022
  • Construction end12 months lateforecast Dec 30, 2022

Also in Cochrane