Replace sidewalk with community multi-use-path

Waterloo, Ontario

completeActive TransportationCVRIS
Federal contribution
$108,000
Federal share80%

of $135.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Waterloo
Construction start
Jul 4, 2022(actual)
Construction end
Aug 18, 2022(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Sep 30, 2022