Accessibility improvement of Button Factory
Federal contribution
$616,000
Federal share80%
of $770.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Waterloo
- Construction start
- Oct 1, 2021(actual)
- Construction end
- Nov 24, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2021
- Construction end13 months earlyforecast Dec 31, 2023