1st and Veterans Way Outdoor Sports Complex
Federal contribution
$4.0M
$3,961,384
Federal share34%
of $11.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2021
2022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Brandon
- Construction start
- Jan 17, 2023(actual)
- Construction end
- Aug 27, 2025(actual)
Against the original forecast
- Construction start7 weeks lateforecast Nov 30, 2022
- Construction end3 months earlyforecast Dec 1, 2025
Also in Brandon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60271 in the federal list. How to read these figures.