Municipal Operations Complex
Federal contribution
$418,600
Federal share83%
of $506.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Saint John
- Construction start
- Aug 9, 2021(actual)
- Construction end
- May 24, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 20, 2021
- Construction end5 months lateforecast Dec 31, 2021
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60303 in the federal list. How to read these figures.