Municipal Operations Complex

Saint John, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$418,600
Federal share83%

of $506.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Saint John
Construction start
Aug 9, 2021(actual)
Construction end
May 24, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 20, 2021
  • Construction end5 months lateforecast Dec 31, 2021