Schedule

Announced and approvedMay 6, 2021
today
2022202420262028
BuiltForecast

Approved 2 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Village of Fort Simpson
Construction start
Jun 1, 2024(actual)
Construction end
Nov 30, 2027(forecast)