Waste Water Treatment Facilities - Roof Upgrades
Federal contribution
$522,934
Federal share75%
of $698.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Saint John
- Construction start
- Feb 14, 2022(actual)
- Construction end
- Apr 10, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Oct 14, 2021
- Construction end3 months lateforecast Dec 31, 2022
Also in Saint John