Back to projects

Waste Water Treatment Facilities - Roof Upgrades

Saint John, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$522,934
Federal share75%

of $698.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Saint John
Construction start
Feb 14, 2022(actual)
Construction end
Apr 10, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Oct 14, 2021
  • Construction end3 months lateforecast Dec 31, 2022

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60325 in the federal list. How to read these figures.