Upgrading of services
Federal contribution
$400,000
Federal share80%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Laval
- Construction start
- Jun 25, 2021(actual)
- Construction end
- Feb 10, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 17, 2021
Also in Laval
- The Société de transport de Laval garage expansion (Phase IV)$85.1M
- Acquisition of 94 Electric Buses$59.5M
- Updating drinking water treatment plants in Laval$46.8M
- Stabilization and revitalization work on the shore and Boulevard des Mille-Îles between Highway 25 and the eastern tip of Laval Island$25.3M
- Backflow controls of Monty sector - Laval$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60326 in the federal list. How to read these figures.