Repair of windows and stairs

Laval, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$3.0M
$2,960,000
Federal share80%

of $3.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 25, 2021(actual)
Construction end
Jan 30, 2022(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Jan 15, 2022