Renovation of sanitary blocks

Laval, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$395,915
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 25, 2021(actual)
Construction end
Jan 31, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Nov 30, 2021