Hillside Pines Home for Special Care - Dining Room Expansion

Bridgewater, Nova Scotia

completeHealthcare InfrastructureCVRIS
Federal contribution
$469,200
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
20222023
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 2, 2022(actual)
Construction end
Sep 5, 2023(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Sep 30, 2023

Also in Bridgewater

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60410 in the federal list. How to read these figures.