Valley View Villa - Facility Upgrades
Federal contribution
$127,147
Federal share80%
of $158.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Valley View Villa
- Construction start
- Dec 20, 2021(actual)
- Construction end
- Apr 30, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 15, 2021
- Construction end4 weeks lateforecast Mar 31, 2022