Ottawa - Alternative Secondary School Program

Ottawa, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$44,640
Federal share80%

of $55.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 4, 2022(actual)
Construction end
Dec 30, 2022(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 19, 2021
  • Construction end9 months lateforecast Mar 31, 2022