Cowichan Valley Trail - Glenora Trails Head Park to Kinsol Trestle Trail Improvements

Cowichan Valley, British Columbia

completeActive TransportationCVRIS
Federal contribution
$240,000
Federal share80%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 14, 2022(actual)
Construction end
Feb 24, 2023(actual)

Against the original forecast

  • Construction start10 months lateforecast Apr 30, 2021
  • Construction end8 weeks lateforecast Dec 30, 2022

Also in Cowichan Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60523 in the federal list. How to read these figures.