Schedule

Announced and approvedAug 10, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 2, 2022(actual)
Construction end
Mar 28, 2023(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Aug 15, 2022
  • Construction end6 months lateforecast Sep 15, 2022