Back to projects

Leduc Storm Manhole Installation

Leduc, Alberta

completeDisaster MitigationCVRIS
Federal contribution
$142,220
Federal share80%

of $177.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Leduc
Construction start
Jul 20, 2021(actual)
Construction end
Dec 14, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 1, 2021
  • Construction end6 weeks lateforecast Oct 30, 2021

Also in Leduc

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60591 in the federal list. How to read these figures.