Leduc Storm Manhole Installation
Federal contribution
$142,220
Federal share80%
of $177.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Leduc
- Construction start
- Jul 20, 2021(actual)
- Construction end
- Dec 14, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 1, 2021
- Construction end6 weeks lateforecast Oct 30, 2021
Also in Leduc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60591 in the federal list. How to read these figures.