Leduc Corinthia Skate Park Rehabilitation
Federal contribution
$106,112
Federal share80%
of $132.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Leduc
- Construction start
- Sep 9, 2021(actual)
- Construction end
- Sep 28, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast May 25, 2021
- Construction end3 months lateforecast Jun 25, 2021