Leduc Elks Drawdown Well
Federal contribution
$139,150
Federal share80%
of $173.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Leduc
- Construction start
- Jul 2, 2021(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2021
Also in Leduc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60593 in the federal list. How to read these figures.