Back to projects

Municipal Operations Complex - HVAC Replacement

Saint John, New Brunswick

completeVentilationCVRIS
Federal contribution
$84,000
Federal share72%

of $117.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
City of Saint John
Construction start
Sep 7, 2021(actual)
Construction end
Nov 15, 2022(actual)

Against the original forecast

  • Construction end4 months lateforecast Jul 31, 2022

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60604 in the federal list. How to read these figures.