City Market Pedway

Saint John, New Brunswick

completeVentilationCVRIS
Federal contribution
$12,895
Federal share80%

of $16.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
City of Saint John
Construction start
Aug 15, 2021(actual)
Construction end
May 24, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2021
  • Construction end5 months lateforecast Dec 15, 2021

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60610 in the federal list. How to read these figures.