City Market Pedway
Federal contribution
$12,895
Federal share80%
of $16.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Saint John
- Construction start
- Aug 15, 2021(actual)
- Construction end
- May 24, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2021
- Construction end5 months lateforecast Dec 15, 2021
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60610 in the federal list. How to read these figures.