Community Centre/Emergency Hub Water Diversion

Blind River, Ontario

completeRecreationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Blind River
Construction start
Oct 7, 2021(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction end6 months earlyforecast Dec 31, 2022