Lunenburg County Lifestyle Centre - Efficiency Retrofits and Solar
Federal contribution
$738,780
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2021
202220232024
Built
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Lunenburg County Multi Purpose Centre Corporation
- Construction start
- Sep 27, 2021(actual)
- Construction end
- Feb 7, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2021
- Construction end7 weeks earlyforecast Mar 29, 2024
Also in Bridgewater
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60713 in the federal list. How to read these figures.