Children's Educational Gallery at Lincoln Museum and Cultural Centre
Federal contribution
$106,370
Federal share40%
of $265.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Lincoln
- Construction start
- Aug 9, 2023(actual)
- Construction end
- Feb 1, 2024(actual)
Against the original forecast
- Construction start14 months lateforecast Jun 17, 2022
- Construction end2 months lateforecast Nov 30, 2023
Also in Lincoln
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60776 in the federal list. How to read these figures.