Accessible Pathways

Huntsville, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
Built

Approved 2 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 15, 2021(actual)
Construction end
Dec 10, 2021(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 1, 2021
  • Construction end5 weeks earlyforecast Jan 12, 2022

Also in Huntsville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60950 in the federal list. How to read these figures.