Phibbs Transit Exchange Upgrade

Vancouver, British Columbia

completePublic TransitPTIS
Federal contribution
$11.1M
$11,137,403
Federal share45%

of $24.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
202220232024
Built

Approved 11 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Oct 21, 2022(actual)
Construction end
Jun 28, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 15, 2022