Burrard SkyTrain Station Upgrade
Federal contribution
$5.4M
$5,417,687
Federal share50%
of $10.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
202220232024
Built
Approved 3 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Province of British Columbia
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Jul 3, 2024(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Jul 30, 2024
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60987 in the federal list. How to read these figures.