Emergency Backup Generator

Cartwright, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$52,596
Federal share40%

of $131.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Cartwright
Construction start
Oct 1, 2023(actual)
Construction end
Feb 28, 2024(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2023
  • Construction end3 months lateforecast Nov 25, 2023