Trail-Memorial Centre-Old Library Retrofit

Trail, British Columbia

completeRecreationCVRIS
Federal contribution
$537,648
Federal share80%

of $672.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Trail
Construction start
Oct 24, 2021(actual)
Construction end
Nov 15, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 20, 2021
  • Construction end4 weeks earlyforecast Dec 15, 2022

Also in Trail

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61058 in the federal list. How to read these figures.