Trail - Memorial Centre Energy Recovery and Retrofits
Federal contribution
$1.4M
$1,411,464
Federal share40%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2023
202420252026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Trail
- Construction start
- Jul 22, 2024(actual)
- Construction end
- Aug 15, 2026(forecast)
Against the original forecast
- Construction start5 weeks lateforecast Jun 16, 2024
Also in Trail
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66988 in the federal list. How to read these figures.