Columbia Pollution Control Centre Upgrade to Secondary Treatment

Trail, British Columbia

completeWastewaterCWWF
Federal contribution
$785,997
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Apr 3, 2017(actual)
Construction end
Mar 15, 2019(actual)

Against the original forecast

  • Construction end11 months lateforecast Mar 31, 2018