Schedule
Announced and approvedFeb 9, 2023
202320242025
Built
Approved 2 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Greater Trail Community Skills Centre Society
- Construction start
- May 1, 2023(actual)
- Construction end
- Dec 17, 2024(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2022
- Construction end7 months lateforecast May 31, 2024