Back to projects

Skills Centre Eco-Renovation

Trail, British Columbia

completeOtherGICB
Federal contribution
$2.4M
$2,395,473
Federal share49%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2023
202320242025
Built

Approved 2 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
May 1, 2023(actual)
Construction end
Dec 17, 2024(actual)

Against the original forecast

  • Construction start6 months lateforecast Nov 1, 2022
  • Construction end7 months lateforecast May 31, 2024