Bike Rack Community Art Installations

Chatham-Kent, Ontario

completeActive TransportationCVRIS
Federal contribution
$43,619
Federal share80%

of $54.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
202220232024
Built

Approved 2 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 20, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 1, 2022

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61061 in the federal list. How to read these figures.